Dept. of Trans. PROGRESS Serial No. Contract No. 25-022-14-40 05-1H3104 PROGRESS PAYMENT VOUCHER %complete: %time: 59% 50% Location: Federal Project: 05-SB-154-R5.7/R6.2 ACST-S154(3) Progress payment No. 006 Payment period ending: 01-20-25 GRANITE CONSTRUCTION COMPANY PO BOX 742478 LOS ANGELES CA 90074-2478 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 4,138,199.50 1,116,216.81 2. a. Extra Work 17,894.97 8,789.00 b. Adustment Comp. -10,526.10 0.00 3. Materials on Hand 64,714.65 0.00 4. Earned Subject to Retention 4,210,283.02 1,125,005.81 5. Mobilization 804,282.00 40,214.10 6. Total Work Completed 4,949,850.37 7. Deductions -12,000.00 54,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 5,002,565.02 1,219,219.91 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,219,219.91