Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 25-183-14-28 05-1H3104 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 05-SB-154-R5.7/R6.2 ACST-S154(3) Progress payment No. 012 Payment period ending: 06-19-25 GRANITE CONSTRUCTION COMPANY PO BOX 742478 LOS ANGELES CA 90074-2478 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 6,689,560.97 13,844.03 2. a. Extra Work 877,302.56 518,468.01 b. Adustment Comp. 11,981.19 -28,111.07 3. Materials on Hand 4. Earned Subject to Retention 7,578,844.72 504,200.97 5. Mobilization 804,282.00 0.00 6. Total Work Completed 8,383,126.72 7. Deductions -89,736.13 -52,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 8,293,390.59 452,200.97 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 452,200.97