Dept. of Trans. PROGRESS Serial No. Contract No. 25-021-10-27 05-1H4304 PROGRESS PAYMENT VOUCHER %complete: %time: 76% 53% Location: Federal Project: 05-SB-101-21.4/21.9 ACNH-Q101(410) Progress payment No. 020 Payment period ending: 01-20-25 MCM CONSTRUCTION INC PO BOX 620 NORTH HIGHLANDS CA 95660 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 13,101,347.00 610,891.40 2. a. Extra Work 599,081.08 12,379.40 b. Adustment Comp. 13,662.56 0.00 3. Materials on Hand 21,740.02 0.00 4. Earned Subject to Retention 13,735,830.66 623,270.80 5. Mobilization 1,980,000.00 0.00 6. Total Work Completed 15,694,090.64 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 15,715,830.66 623,270.80 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 623,270.80