Dept. of Trans. PROGRESS Serial No. Contract No. 22-115-16-45 05-1H4604 PROGRESS PAYMENT VOUCHER %complete: %time: 18% 27% Location: Federal Project: 05-MON-1-63.0/63.0 NONE Progress payment No. 009 Payment period ending: 04-20-22 FEC FUTURE CONTRACTORS AND ENGINEERS INC 184 TECHNOLOGY DRIVE #205 IRVINE CA 92618 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 682,465.36 54,303.18 2. a. Extra Work 43,947.86 6,574.25 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 726,413.22 60,877.43 5. Mobilization 466,650.00 0.00 6. Total Work Completed 1,193,063.22 7. Deductions 0.00 10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,193,063.22 70,877.43 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 70,877.43