Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 24-018-19-07 05-1H4804 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 05-SCR-1-13.3 NONE Progress payment No. 006 Payment period ending: 12-29-23 GRANITE CONSTRUCTION COMPANY PO BOX 742478 LOS ANGELES CA 90074-2478 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 994,215.26 24,870.25 2. a. Extra Work 51,417.84 13,571.83 b. Adustment Comp. -998.40 0.00 3. Materials on Hand 4. Earned Subject to Retention 1,044,634.70 38,442.08 5. Mobilization 97,667.00 0.00 6. Total Work Completed 1,142,301.70 7. Deductions -30,000.00 -30,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,112,301.70 8,442.08 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 8,442.08