Dept. of Trans. PROGRESS Serial No. Contract No. 21-355-16-10 05-1H6304 PROGRESS PAYMENT VOUCHER %complete: %time: 65% 32% Location: Federal Project: 05-SB-154-21.3 NONE Progress payment No. 005 Payment period ending: 12-20-21 TAYLOR JANE CONSTRUCTION LP PO BOX 1327 NIPOMO CA 93444 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 487,710.30 28,044.50 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 487,710.30 28,044.50 5. Mobilization 40,000.00 0.00 6. Total Work Completed 527,710.30 7. Deductions -25,755.30 -23,755.30 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 501,955.00 4,289.20 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 4,289.20