Dept. of Trans. PROGRESS Serial No. Contract No. 24-170-07-18 05-1H6904 PROGRESS PAYMENT VOUCHER %complete: %time: 51% 51% Location: Federal Project: 05-MON-101-R91.3/98.8 ACNH-Q101(411) 05-MON-101-100.3/101.3 Progress payment No. 012 Payment period ending: 06-13-24 DESILVA GATES CONSTRUCTION LP 11555 DUBLIN BLVD DUBLIN CA 94568 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 13,060,620.94 3,888,900.07 2. a. Extra Work 476,566.23 168,069.88 b. Adustment Comp. 143,615.76 25,001.77 3. Materials on Hand 513,913.00 -80,277.00 4. Earned Subject to Retention 14,194,715.93 4,001,694.72 5. Mobilization 3,129,300.00 0.00 6. Total Work Completed 16,810,102.93 7. Deductions -10,000.00 18,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 17,314,015.93 4,019,694.72 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 4,019,694.72