Dept. of Trans. PROGRESS Serial No. Contract No. 24-261-15-23 05-1H6904 PROGRESS PAYMENT VOUCHER %complete: %time: 83% 68% Location: Federal Project: 05-MON-101-R91.3/98.8 ACNH-Q101(411) 05-MON-101-100.3/101.3 Progress payment No. 015 Payment period ending: 09-13-24 DESILVA GATES CONSTRUCTION LP 11555 DUBLIN BLVD DUBLIN CA 94568 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 23,419,326.52 3,728,232.71 2. a. Extra Work 954,028.69 8,594.88 b. Adustment Comp. 1,431,615.76 -37,000.00 3. Materials on Hand 328,485.06 1,059.00 4. Earned Subject to Retention 26,133,456.03 3,700,886.59 5. Mobilization 3,294,000.00 0.00 6. Total Work Completed 29,098,970.97 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 29,427,456.03 3,700,886.59 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 3,700,886.59