Dept. of Trans. PROGRESS Serial No. Contract No. 24-295-11-12 05-1H6904 PROGRESS PAYMENT VOUCHER %complete: %time: 89% 76% Location: Federal Project: 05-MON-101-R91.3/98.8 ACNH-Q101(411) 05-MON-101-100.3/101.3 Progress payment No. 016 Payment period ending: 10-20-24 DESILVA GATES CONSTRUCTION LP 11555 DUBLIN BLVD DUBLIN CA 94568 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 25,132,545.12 1,713,218.60 2. a. Extra Work 1,073,453.71 119,425.02 b. Adustment Comp. 1,431,615.76 0.00 3. Materials on Hand 323,479.06 -5,006.00 4. Earned Subject to Retention 27,961,093.65 1,827,637.62 5. Mobilization 3,294,000.00 0.00 6. Total Work Completed 30,931,614.59 7. Deductions -10,000.00 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 31,245,093.65 1,817,637.62 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,817,637.62