Dept. of Trans. PROGRESS Serial No. Contract No. 22-032-09-25 05-1H8504 PROGRESS PAYMENT VOUCHER %complete: %time: 22% 30% Location: Federal Project: 05-SB-101-70.7/91.0 ACNH-Q101(396) 05-SLO-101-4.7/5.0 Progress payment No. 003 Payment period ending: 01-20-22 A M CONCRETE INC PO BOX 3367 THOUSAND OAKS CA 91359 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 663,331.51 335,470.88 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 663,331.51 335,470.88 5. Mobilization 284,397.00 94,799.00 6. Total Work Completed 947,728.51 7. Deductions -4,000.00 26,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 943,728.51 456,269.88 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 456,269.88