Dept. of Trans. PROGRESS Serial No. Contract No. 25-108-13-01 05-1H8604 PROGRESS PAYMENT VOUCHER %complete: %time: 72% 75% Location: Federal Project: 05-SB-101-46.2/R52.3 ACNH-Q101(409) Progress payment No. 025 Payment period ending: 04-17-25 CALPORTLAND CONSTRUCTION 1625 E DONOVAN RD SANTA MARIA CA 93454 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 28,600,566.08 383,725.32 2. a. Extra Work 3,620,385.89 105,511.96 b. Adustment Comp. 199,917.06 -12,191.10 3. Materials on Hand 176,391.00 -50,670.00 4. Earned Subject to Retention 32,597,260.03 426,376.18 5. Mobilization 2,525,000.00 0.00 6. Total Work Completed 34,945,869.03 7. Deductions -16,000.00 10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 35,106,260.03 436,376.18 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 436,376.18