Dept. of Trans. PROGRESS Serial No. Contract No. 25-356-10-10 05-1H8604 PROGRESS PAYMENT VOUCHER %complete: %time: 89% 97% Location: Federal Project: 05-SB-101-46.2/R52.3 ACNH-Q101(409) Progress payment No. 033 Payment period ending: 12-20-25 CALPORTLAND CONSTRUCTION 1625 E DONOVAN RD SANTA MARIA CA 93454 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 37,123,135.50 455,999.12 2. a. Extra Work 7,839,009.20 90,950.76 b. Adustment Comp. 4,023.27 -231,875.67 3. Materials on Hand 4. Earned Subject to Retention 44,966,167.97 315,074.21 5. Mobilization 2,525,000.00 0.00 6. Total Work Completed 47,491,167.97 7. Deductions -20,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 47,471,167.97 315,074.21 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 315,074.21