Dept. of Trans. PROGRESS Serial No. Contract No. 23-298-08-23 05-1H9604 PROGRESS PAYMENT VOUCHER %complete: %time: 21% 14% Location: Federal Project: 05-SB-135-10.6/17.6 HSNH-P135(10) Progress payment No. 005 Payment period ending: 10-20-23 GRANITE CONSTRUCTION COMPANY PO BOX 742478 LOS ANGELES CA 90074-2478 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,464,608.07 1,334,208.47 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 559,695.00 -32,495.00 4. Earned Subject to Retention 3,024,303.07 1,301,713.47 5. Mobilization 1,538,239.50 512,746.50 6. Total Work Completed 4,002,847.57 7. Deductions -83,539.87 -27,846.62 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 4,479,002.70 1,786,613.35 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,786,613.35