Dept. of Trans. PROGRESS Serial No. Contract No. 24-057-21-33 05-1H9604 PROGRESS PAYMENT VOUCHER %complete: %time: 37% 29% Location: Federal Project: 05-SB-135-10.6/17.6 HSNH-P135(10) Progress payment No. 009 Payment period ending: 02-20-24 GRANITE CONSTRUCTION COMPANY PO BOX 742478 LOS ANGELES CA 90074-2478 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 5,145,644.81 1,047,316.59 2. a. Extra Work 83,320.18 6,804.78 b. Adustment Comp. 3. Materials on Hand 1,081,367.00 -168,308.00 4. Earned Subject to Retention 6,310,331.99 885,813.37 5. Mobilization 1,948,436.70 0.00 6. Total Work Completed 7,177,401.69 7. Deductions -105,817.17 48,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 8,152,951.52 933,813.37 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 933,813.37