Dept. of Trans. PROGRESS Serial No. Contract No. 24-114-13-28 05-1H9604 PROGRESS PAYMENT VOUCHER %complete: %time: 53% 39% Location: Federal Project: 05-SB-135-10.6/17.6 HSNH-P135(10) Progress payment No. 011 Payment period ending: 04-19-24 GRANITE CONSTRUCTION COMPANY PO BOX 742478 LOS ANGELES CA 90074-2478 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 8,166,856.71 1,322,316.72 2. a. Extra Work 274,550.94 79,480.32 b. Adustment Comp. 3. Materials on Hand 900,340.00 -130,729.00 4. Earned Subject to Retention 9,341,747.65 1,271,068.04 5. Mobilization 1,948,436.70 0.00 6. Total Work Completed 10,389,844.35 7. Deductions -105,817.17 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 11,184,367.18 1,271,068.04 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,271,068.04