Dept. of Trans. PROGRESS Serial No. Contract No. 24-169-15-30 05-1H9604 PROGRESS PAYMENT VOUCHER %complete: %time: 64% 51% Location: Federal Project: 05-SB-135-10.6/17.6 HSNH-P135(10) Progress payment No. 013 Payment period ending: 06-13-24 GRANITE CONSTRUCTION COMPANY PO BOX 742478 LOS ANGELES CA 90074-2478 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 10,361,292.00 1,176,095.89 2. a. Extra Work 286,522.85 9,316.42 b. Adustment Comp. 3. Materials on Hand 543,861.00 -219,226.00 4. Earned Subject to Retention 11,191,675.85 966,186.31 5. Mobilization 2,050,986.00 0.00 6. Total Work Completed 12,698,800.85 7. Deductions -111,386.50 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 13,131,275.35 966,186.31 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 966,186.31