Dept. of Trans. SEMI-FINAL Serial No. Contract No. 20-234-10-42 05-1J0404 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 05-SLO-46-49.5 NONE 05-MON-101-R3.1 05-MON-101-R5.2 Progress payment No. 006 Payment period ending: 07-16-20 HOSELEY CORPORATION PO BOX 881386 SAN FRANCISCO CA 94188 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,455,796.50 0.00 2. a. Extra Work 20,211.17 1,238.67 b. Adustment Comp. 4,175.85 0.00 3. Materials on Hand 4. Earned Subject to Retention 1,480,183.52 1,238.67 5. Mobilization 150,000.00 0.00 6. Total Work Completed 1,630,183.52 7. Deductions 0.00 6,648.76 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,630,183.52 7,887.43 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 7,887.43