Dept. of Trans. PROGRESS Serial No. Contract No. 18-127-08-58 05-1J0804 PROGRESS PAYMENT VOUCHER %complete: %time: 65% 70% Location: Federal Project: 05-SCR-17-5.8/12.5 NONE Progress payment No. 008 Payment period ending: 05-04-18 GRANITE ROCK COMPANY 120 GRANITE ROCK WAY SAN JOSE CA 95136 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 968,976.88 168,808.43 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 968,976.88 168,808.43 5. Mobilization 6. Total Work Completed 968,976.88 7. Deductions -10,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 958,976.88 168,808.43 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 168,808.43