Dept. of Trans. SEMI-FINAL Serial No. Contract No. 18-346-13-31 05-1J0804 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 05-SCR-17-5.8/12.5 NONE Progress payment No. 012 Payment period ending: 11-13-18 GRANITE ROCK COMPANY 120 GRANITE ROCK WAY SAN JOSE CA 95136 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 1,192,242.17 114,512.26 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 1,192,242.17 114,512.26 5. Mobilization 6. Total Work Completed 1,192,242.17 7. Deductions -20,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,172,242.17 114,512.26 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 114,512.26