Dept. of Trans. PROGRESS Serial No. Contract No. 17-172-13-38 05-1J1004 PROGRESS PAYMENT VOUCHER %complete: %time: 34% 100% Location: Federal Project: 05-SB-101-0.0 NONE Progress payment No. 002 Payment period ending: 06-20-17 SOUZA CONSTRUCTION INC PO BOX 3810 SAN LUIS OBISPO CA 934033810 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 401,249.77 219,636.01 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 401,249.77 219,636.01 5. Mobilization 6. Total Work Completed 401,249.77 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 401,249.77 219,636.01 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 219,636.01