Dept. of Trans. SEMI-FINAL Serial No. Contract No. 25-114-15-00 05-1J4604 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 05-MON-68-2.8/3.1 HSNH-P068(779) Progress payment No. 012 Payment period ending: 03-22-24 GRANITE ROCK COMPANY 5225 HELLYER AVENUE #220 SAN JOSE CA 95138 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,294,796.42 0.00 2. a. Extra Work 294,124.43 22,844.21 b. Adustment Comp. -54,234.50 0.00 3. Materials on Hand 4. Earned Subject to Retention 1,534,686.35 22,844.21 5. Mobilization 120,600.00 0.00 6. Total Work Completed 1,655,286.35 7. Deductions -223,156.94 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,432,129.41 22,844.21 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 22,844.21