Dept. of Trans. PROGRESS Serial No. Contract No. 23-205-21-45 05-1J4804 PROGRESS PAYMENT VOUCHER %complete: %time: 48% 50% Location: Federal Project: 05-SBT-25-54.0 SNHG-P025(33) Progress payment No. 014 Payment period ending: 07-20-23 GRANITE ROCK COMPANY 5225 HELLYER AVENUE #220 SAN JOSE CA 95138 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,702,996.98 912,350.15 2. a. Extra Work 448,901.19 112,106.81 b. Adustment Comp. 9,786.23 -6,044.97 3. Materials on Hand 35,300.00 35,300.00 4. Earned Subject to Retention 4,196,984.40 1,053,711.99 5. Mobilization 812,250.00 0.00 6. Total Work Completed 4,973,934.40 7. Deductions -5,000.00 45,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 5,004,234.40 1,098,711.99 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,098,711.99