Dept. of Trans. PROGRESS Serial No. Contract No. 23-298-08-36 05-1J4804 PROGRESS PAYMENT VOUCHER %complete: %time: 64% 80% Location: Federal Project: 05-SBT-25-54.0 SNHG-P025(33) Progress payment No. 018 Payment period ending: 10-20-23 GRANITE ROCK COMPANY 5225 HELLYER AVENUE #220 SAN JOSE CA 95138 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 5,335,257.21 710,948.90 2. a. Extra Work 516,027.39 13,423.97 b. Adustment Comp. -11,691.88 -21,478.11 3. Materials on Hand 4. Earned Subject to Retention 5,839,592.72 702,894.76 5. Mobilization 855,000.00 0.00 6. Total Work Completed 6,694,592.72 7. Deductions -160,434.21 -115,434.21 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 6,534,158.51 587,460.55 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 587,460.55