Dept. of Trans. PROGRESS Serial No. Contract No. 23-331-19-41 05-1J4804 PROGRESS PAYMENT VOUCHER %complete: %time: 76% 88% Location: Federal Project: 05-SBT-25-54.0 SNHG-P025(33) Progress payment No. 019 Payment period ending: 11-20-23 GRANITE ROCK COMPANY 5225 HELLYER AVENUE #220 SAN JOSE CA 95138 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 6,490,461.84 1,155,204.63 2. a. Extra Work 587,238.16 71,210.77 b. Adustment Comp. -26,541.06 -14,849.18 3. Materials on Hand 4. Earned Subject to Retention 7,051,158.94 1,211,566.22 5. Mobilization 855,000.00 0.00 6. Total Work Completed 7,906,158.94 7. Deductions -206,734.93 -46,300.72 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 7,699,424.01 1,165,265.50 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,165,265.50