Dept. of Trans. SEMI-FINAL Serial No. Contract No. 24-351-14-49 05-1J4804 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 05-SBT-25-54.0 SNHG-P025(33) Progress payment No. 026 Payment period ending: 04-19-24 GRANITE ROCK COMPANY 5225 HELLYER AVENUE #220 SAN JOSE CA 95138 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 8,974,298.89 0.00 2. a. Extra Work 672,299.42 0.00 b. Adustment Comp. -184,597.02 0.00 3. Materials on Hand 4. Earned Subject to Retention 9,462,001.29 0.00 5. Mobilization 855,000.00 0.00 6. Total Work Completed 10,317,001.29 7. Deductions -238,081.29 26,198.59 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 10,078,920.00 26,198.59 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 26,198.59