Dept. of Trans. PROGRESS Serial No. Contract No. 19-295-13-24 05-1J5304 PROGRESS PAYMENT VOUCHER %complete: %time: 77% 72% Location: Federal Project: 05-MON-1-0.0 NONE 05-MON-101-0.0 05-SCR-1-0.0 Progress payment No. 004 Payment period ending: 10-20-19 RV CONCRETE INC 605 E COMMERCIAL ST ANAHEIM CA 92801 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 823,940.98 39,105.00 2. a. Extra Work b. Adustment Comp. -2,558.65 -2,558.65 3. Materials on Hand 4. Earned Subject to Retention 821,382.33 36,546.35 5. Mobilization 120,000.00 0.00 6. Total Work Completed 941,382.33 7. Deductions -15,377.84 -9,096.43 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 926,004.49 27,449.92 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 27,449.92