Dept. of Trans. PROGRESS Serial No. Contract No. 20-023-14-02 05-1J5304 PROGRESS PAYMENT VOUCHER %complete: %time: 77% 84% Location: Federal Project: 05-MON-1-0.0 NONE 05-MON-101-0.0 05-SCR-1-0.0 Progress payment No. 005 Payment period ending: 01-20-20 RV CONCRETE INC 605 E COMMERCIAL ST ANAHEIM CA 92801 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 823,940.98 0.00 2. a. Extra Work b. Adustment Comp. -2,558.65 0.00 3. Materials on Hand 4. Earned Subject to Retention 821,382.33 0.00 5. Mobilization 120,000.00 0.00 6. Total Work Completed 941,382.33 7. Deductions -7,635.57 7,742.27 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 933,746.76 7,742.27 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 7,742.27