Dept. of Trans. PROGRESS Serial No. Contract No. 18-129-13-31 05-1J6504 PROGRESS PAYMENT VOUCHER %complete: %time: 85% 72% Location: Federal Project: 05-SB-101-1.6/4.0 NONE Progress payment No. 002 Payment period ending: 05-09-18 SECURITY PAVING COMPANY INC 13170 TELFAIR AVE SYLMAR CA 91342 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 664,463.15 320,026.82 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 664,463.15 320,026.82 5. Mobilization 6. Total Work Completed 664,463.15 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 664,463.15 320,026.82 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 320,026.82