Dept. of Trans. PROGRESS Serial No. Contract No. 18-233-10-26 05-1J6704 PROGRESS PAYMENT VOUCHER %complete: %time: 1% 6% Location: Federal Project: 05-SB-192-15.4/15.6 NONE Progress payment No. 002 Payment period ending: 08-20-18 LASH CONSTRUCTION INC PO BOX 4640 SANTA BARBARA CA 93140 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 140,451.55 55,777.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 140,451.55 55,777.00 5. Mobilization 6. Total Work Completed 140,451.55 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 140,451.55 55,777.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 55,777.00