Dept. of Trans. PROGRESS Serial No. Contract No. 25-108-13-14 05-1J7804 PROGRESS PAYMENT VOUCHER %complete: %time: 17% 17% Location: Federal Project: 05-SLO-101-61.7/62.1 HSNH-Q101(429) Progress payment No. 004 Payment period ending: 04-20-24 CALPORTLAND CONSTRUCTION 1625 E DONOVAN RD SANTA MARIA CA 93454 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,571,916.01 1,056,314.65 2. a. Extra Work 1,104.52 0.00 b. Adustment Comp. 3. Materials on Hand 331,650.00 30,150.00 4. Earned Subject to Retention 1,904,670.53 1,086,464.65 5. Mobilization 562,500.00 187,500.00 6. Total Work Completed 2,135,520.53 7. Deductions -10,000.00 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 2,457,170.53 1,263,964.65 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,263,964.65