Dept. of Trans. PROGRESS Serial No. Contract No. 25-203-13-55 05-1J7804 PROGRESS PAYMENT VOUCHER %complete: %time: 39% 42% Location: Federal Project: 05-SLO-101-61.7/62.1 HSNH-Q101(429) Progress payment No. 007 Payment period ending: 07-20-24 CALPORTLAND CONSTRUCTION 1625 E DONOVAN RD SANTA MARIA CA 93454 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,962,493.38 610,411.99 2. a. Extra Work 156,413.93 2,772.19 b. Adustment Comp. -12,700.83 0.00 3. Materials on Hand 211,180.20 60,430.20 4. Earned Subject to Retention 4,317,386.68 673,614.38 5. Mobilization 712,500.00 0.00 6. Total Work Completed 4,818,706.48 7. Deductions -200,429.00 -120,429.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 4,829,457.68 553,185.38 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 553,185.38