Dept. of Trans. PROGRESS Serial No. Contract No. 25-237-12-27 05-1J7804 PROGRESS PAYMENT VOUCHER %complete: %time: 46% 52% Location: Federal Project: 05-SLO-101-61.7/62.1 HSNH-Q101(429) Progress payment No. 008 Payment period ending: 08-20-25 CALPORTLAND CONSTRUCTION 1625 E DONOVAN RD SANTA MARIA CA 93454 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 4,950,943.90 988,450.52 2. a. Extra Work 163,616.73 7,202.80 b. Adustment Comp. -12,700.83 0.00 3. Materials on Hand 211,180.20 0.00 4. Earned Subject to Retention 5,313,040.00 995,653.32 5. Mobilization 712,500.00 0.00 6. Total Work Completed 5,814,359.80 7. Deductions -201,904.20 -1,475.20 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 5,823,635.80 994,178.12 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 994,178.12