Dept. of Trans. PROGRESS Serial No. Contract No. 25-295-07-47 05-1J7804 PROGRESS PAYMENT VOUCHER %complete: %time: 56% 68% Location: Federal Project: 05-SLO-101-61.7/62.1 HSNH-Q101(429) Progress payment No. 010 Payment period ending: 10-20-25 CALPORTLAND CONSTRUCTION 1625 E DONOVAN RD SANTA MARIA CA 93454 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 6,043,006.00 350,579.68 2. a. Extra Work 262,550.71 98,933.98 b. Adustment Comp. -17,345.47 -4,644.64 3. Materials on Hand 211,180.20 0.00 4. Earned Subject to Retention 6,499,391.44 444,869.02 5. Mobilization 750,000.00 0.00 6. Total Work Completed 7,038,211.24 7. Deductions -30,742.50 131,904.20 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 7,218,648.94 576,773.22 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 576,773.22