Dept. of Trans. PROGRESS Serial No. Contract No. 25-357-13-50 05-1J7804 PROGRESS PAYMENT VOUCHER %complete: %time: 66% 82% Location: Federal Project: 05-SLO-101-61.7/62.1 HSNH-Q101(429) Progress payment No. 012 Payment period ending: 12-20-25 CALPORTLAND CONSTRUCTION 1625 E DONOVAN RD SANTA MARIA CA 93454 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 7,296,208.90 667,021.35 2. a. Extra Work 262,550.71 0.00 b. Adustment Comp. -17,345.47 0.00 3. Materials on Hand 0.00 -60,430.20 4. Earned Subject to Retention 7,541,414.14 606,591.15 5. Mobilization 750,000.00 0.00 6. Total Work Completed 8,291,414.14 7. Deductions -2,742.50 8,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 8,288,671.64 614,591.15 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 614,591.15