Dept. of Trans. PROGRESS Serial No. Contract No. 26-023-14-27 05-1J7804 PROGRESS PAYMENT VOUCHER %complete: %time: 68% 84% Location: Federal Project: 05-SLO-101-61.7/62.1 HSNH-Q101(429) Progress payment No. 013 Payment period ending: 01-20-26 CALPORTLAND CONSTRUCTION 1625 E DONOVAN RD SANTA MARIA CA 93454 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 7,659,118.52 362,909.62 2. a. Extra Work 269,155.92 6,605.21 b. Adustment Comp. -17,345.47 0.00 3. Materials on Hand 4. Earned Subject to Retention 7,910,928.97 369,514.83 5. Mobilization 750,000.00 0.00 6. Total Work Completed 8,660,928.97 7. Deductions -2,742.50 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 8,658,186.47 369,514.83 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 369,514.83