Dept. of Trans. PROGRESS Serial No. Contract No. 26-085-13-00 05-1J7804 PROGRESS PAYMENT VOUCHER %complete: %time: 80% 97% Location: Federal Project: 05-SLO-101-61.7/62.1 HSNH-Q101(429) Progress payment No. 015 Payment period ending: 03-20-26 CALPORTLAND CONSTRUCTION 1625 E DONOVAN RD SANTA MARIA CA 93454 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 9,597,085.95 1,370,596.94 2. a. Extra Work 269,155.92 0.00 b. Adustment Comp. -17,345.47 0.00 3. Materials on Hand 4. Earned Subject to Retention 9,848,896.40 1,370,596.94 5. Mobilization 750,000.00 0.00 6. Total Work Completed 10,598,896.40 7. Deductions -70,742.50 -38,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions -137,059.69 -137,059.69 c. Reduction after 95% Comp. 9. Total pay to Contractor 10,391,094.21 1,195,537.25 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,195,537.25