Dept. of Trans. PROGRESS Serial No. Contract No. 26-141-12-35 05-1J7804 PROGRESS PAYMENT VOUCHER %complete: %time: 96% 100% Location: Federal Project: 05-SLO-101-61.7/62.1 HSNH-Q101(429) Progress payment No. 017 Payment period ending: 05-20-26 CALPORTLAND CONSTRUCTION 1625 E DONOVAN RD SANTA MARIA CA 93454 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 11,049,223.32 175,334.88 2. a. Extra Work 379,938.51 91,591.82 b. Adustment Comp. -37,608.33 -75,162.86 3. Materials on Hand 4. Earned Subject to Retention 11,391,553.50 191,763.84 5. Mobilization 750,000.00 0.00 6. Total Work Completed 12,141,553.50 7. Deductions -507,312.82 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 11,634,240.68 191,763.84 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 191,763.84