Dept. of Trans. SEMI-FINAL Serial No. Contract No. 26-174-10-29 05-1J7804 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 05-SLO-101-61.7/62.1 HSNH-Q101(429) Progress payment No. 019 Payment period ending: 05-21-26 CALPORTLAND CONSTRUCTION 1625 E DONOVAN RD SANTA MARIA CA 93454 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 11,145,048.85 2,000.00 2. a. Extra Work 601,160.02 166,525.00 b. Adustment Comp. -33,375.33 0.00 3. Materials on Hand 4. Earned Subject to Retention 11,712,833.54 168,525.00 5. Mobilization 750,000.00 0.00 6. Total Work Completed 12,462,833.54 7. Deductions -212,873.53 438,245.82 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 12,249,960.01 606,770.82 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 606,770.82