Dept. of Trans. SEMI-FINAL Serial No. Contract No. 26-246-13-26 05-1J7804 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 05-SLO-101-61.7/62.1 HSNH-Q101(429) Progress payment No. 020 Payment period ending: 05-21-26 CALPORTLAND CONSTRUCTION 1625 E DONOVAN RD SANTA MARIA CA 93454 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 11,156,810.25 11,761.40 2. a. Extra Work 618,996.45 17,836.43 b. Adustment Comp. -33,375.33 0.00 3. Materials on Hand 4. Earned Subject to Retention 11,742,431.37 29,597.83 5. Mobilization 750,000.00 0.00 6. Total Work Completed 12,492,431.37 7. Deductions -102,873.53 110,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 12,389,557.84 139,597.83 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 139,597.83