Dept. of Trans. FINAL Serial No. Contract No. 22-251-16-20 05-1J8504 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 05-SB-101-3.8/3.8 NONE Progress payment No. 008 Payment period ending: 03-29-22 GRANITE CONSTRUCTION COMPANY 3005 JAMES RD BAKERSFIELD CA 93308 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 890,121.10 0.00 2. a. Extra Work 73,414.18 0.00 b. Adustment Comp. -2,680.32 0.00 3. Materials on Hand 4. Earned Subject to Retention 960,854.96 0.00 5. Mobilization 88,000.00 0.00 6. Total Work Completed 1,048,854.96 7. Deductions 0.00 15,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,048,854.96 15,000.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 15,000.00