Dept. of Trans. PROGRESS Serial No. Contract No. 22-054-11-31 05-1K0504 PROGRESS PAYMENT VOUCHER %complete: %time: 46% 21% Location: Federal Project: 05-MON-1-55.7/55.9 STER-31SU(4) Progress payment No. 002 Payment period ending: 02-20-22 GORDON N BALL INC 333 CAMILLE AVE ALAMO CA 94507 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 617,695.00 567,135.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 0.00 -78,240.20 4. Earned Subject to Retention 617,695.00 488,894.80 5. Mobilization 142,500.00 67,500.00 6. Total Work Completed 760,195.00 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 760,195.00 556,394.80 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 556,394.80