Dept. of Trans. PROGRESS Serial No. Contract No. 23-235-14-45 05-1K0704 PROGRESS PAYMENT VOUCHER %complete: %time: 32% 48% Location: Federal Project: 05-SCR-17-8.2 STER-31SA(4) Progress payment No. 005 Payment period ending: 08-20-23 GORDON N BALL INC 333 CAMILLE AVE ALAMO CA 94507 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 440,800.00 211,155.00 2. a. Extra Work 113,530.12 81,129.23 b. Adustment Comp. 3. Materials on Hand 67,113.89 67,113.89 4. Earned Subject to Retention 621,444.01 359,398.12 5. Mobilization 171,000.00 36,000.00 6. Total Work Completed 725,330.12 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 792,444.01 395,398.12 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 395,398.12