Dept. of Trans. PROGRESS Serial No. Contract No. 21-298-13-07 05-1K1304 PROGRESS PAYMENT VOUCHER %complete: %time: 26% 14% Location: Federal Project: 05-SCR-9-20.0/20.0 STER-31TP(4) Progress payment No. 004 Payment period ending: 10-20-21 GORDON N BALL INC 333 CAMILLE AVE ALAMO CA 94507 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 543,219.00 30,909.00 2. a. Extra Work 13,523.65 13,523.65 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 556,742.65 44,432.65 5. Mobilization 217,500.00 0.00 6. Total Work Completed 774,242.65 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 774,242.65 44,432.65 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 44,432.65