Dept. of Trans. PROGRESS Serial No. Contract No. 22-054-16-32 05-1K1304 PROGRESS PAYMENT VOUCHER %complete: %time: 31% 24% Location: Federal Project: 05-SCR-9-20.0/20.0 STER-31TP(4) Progress payment No. 008 Payment period ending: 02-20-22 GORDON N BALL INC 333 CAMILLE AVE ALAMO CA 94507 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 630,876.00 27,757.00 2. a. Extra Work 19,092.10 0.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 649,968.10 27,757.00 5. Mobilization 275,500.00 0.00 6. Total Work Completed 925,468.10 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 925,468.10 27,757.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 27,757.00