Dept. of Trans. PROGRESS Serial No. Contract No. 19-204-14-47 05-1K1404 PROGRESS PAYMENT VOUCHER %complete: %time: 33% 15% Location: Federal Project: 05-SCR-9-15.0/15.0 STER-31LR(4) Progress payment No. 001 Payment period ending: 07-20-19 GORDON N BALL INC 333 CAMILLE AVE ALAMO CA 94507 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 326,895.00 326,895.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 326,895.00 326,895.00 5. Mobilization 114,000.00 114,000.00 6. Total Work Completed 440,895.00 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 440,895.00 440,895.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 440,895.00