Dept. of Trans. PROGRESS Serial No. Contract No. 21-264-19-05 05-1K2804 PROGRESS PAYMENT VOUCHER %complete: %time: 25% 52% Location: Federal Project: 05-SLO-101-35.6/42.0 NONE Progress payment No. 002 Payment period ending: 09-20-21 PAPICH CONSTRUCTION COMPANY INC 398 SUNRISE TERRACE ARROYO GRANDE CA 93420 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 640,693.05 269,061.13 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 640,693.05 269,061.13 5. Mobilization 348,046.65 0.00 6. Total Work Completed 988,739.70 7. Deductions -52,190.02 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 936,549.68 269,061.13 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 269,061.13