Dept. of Trans. PROGRESS Serial No. Contract No. 19-235-08-50 05-1K3304 PROGRESS PAYMENT VOUCHER %complete: %time: 86% 77% Location: Federal Project: 05-SB-101-57.7/63.0 ACNH-Q101(352) Progress payment No. 003 Payment period ending: 08-20-19 GRANITE CONSTRUCTION COMPANY PO BOX 50085 WATSONVILLE CA 95077 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,408,789.66 200,380.65 2. a. Extra Work b. Adustment Comp. -9,861.99 -9,861.99 3. Materials on Hand 4. Earned Subject to Retention 3,398,927.67 190,518.66 5. Mobilization 425,000.00 0.00 6. Total Work Completed 3,823,927.67 7. Deductions -10,000.00 14,696.90 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 3,813,927.67 205,215.56 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 205,215.56