Dept. of Trans. PROGRESS Serial No. Contract No. 23-116-18-19 05-1K3804 PROGRESS PAYMENT VOUCHER %complete: %time: 86% 26% Location: Federal Project: 05-SB-101-12.3/13.2 NONE Progress payment No. 011 Payment period ending: 04-20-23 CENTRAL COAST FINANCIAL GROUP INC 17750 WARDS FERRY RD SONORA CA 95370 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 769,018.50 4,147.00 2. a. Extra Work 28,931.67 0.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 797,950.17 4,147.00 5. Mobilization 6. Total Work Completed 797,950.17 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 797,950.17 4,147.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 4,147.00