Dept. of Trans. PROGRESS Serial No. Contract No. 19-235-08-54 05-1K5904 PROGRESS PAYMENT VOUCHER %complete: %time: 9% 13% Location: Federal Project: 05-SB-101-5.5/10.5 NONE Progress payment No. 003 Payment period ending: 08-20-19 GRANITE CONSTRUCTION COMPANY PO BOX 6744 SANTA BARBARA CA 93160 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 111,122.68 32,517.65 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 111,122.68 32,517.65 5. Mobilization 6. Total Work Completed 111,122.68 7. Deductions -10,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 101,122.68 32,517.65 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 32,517.65