Dept. of Trans. PROGRESS Serial No. Contract No. 22-264-10-04 05-1K7004 PROGRESS PAYMENT VOUCHER %complete: %time: 84% 75% Location: Federal Project: 05-MON-1-64.4/64.4 NONE Progress payment No. 016 Payment period ending: 09-20-22 AMERICAN CIVIL CONSTRUCTORS WEST COAST LLC 2990 BAY VISTA CT #D BENICIA CA 94510 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,357,955.45 260,000.70 2. a. Extra Work 95,146.97 0.00 b. Adustment Comp. -12,048.75 -12,048.75 3. Materials on Hand 4. Earned Subject to Retention 3,441,053.67 247,951.95 5. Mobilization 440,000.00 0.00 6. Total Work Completed 3,881,053.67 7. Deductions -8,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 3,873,053.67 247,951.95 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 247,951.95